| |
| |
|
| |
| |
|
| |
What is PowerStream responsible for? |
|
| |
| Ý |
|
| | |
What is the Generator (Customer) responsible for? |
- The Generator (Customer) is responsible for the safety, design, construction, operation, metering, protection and control, and maintenance of their generating facility
- The Customer must contact all applicable agencies involved and obtain all approvals prior to the connection being permitted
- The Customer must ensure that all necessary submissions and agreements are completed and all required payments have been made to PowerStream Inc.
- The Customer should consider using a consultant to assist with the connection requirements, process and approvals
|
| |
| Ý |
|
| | |
What is the process for connecting a customer owned embedded generator? |
The connection process for a customer owned generator is based on the Generator Classification as shown in the table below: | Classification: | Generator Rating: |
| | Micro | ≤10 kW | | Small | a) ≤ 500 kW connected on distribution system voltage < 15 kV | | | b) ≤ 1 MW connected on distribution system voltage ≥ 15 kV | | Mid-sized | a) < 10 MW but > 500 kW connected on distribution system voltage < 15 kV | | | b) > 1 MW but < 10 MW connected on distribution system voltage ≥15 kV | | Large | ≥ 10 MW |
|
|
| |
Small, Mid-Sized and Large Generators - Connection Process Overview Under FIT Program |
The following is the connection process overview for generators that are greater than 10kW and operate at voltages below 50kV: |
| |
| 1. | Initial Contact |
| | |
| | The Customer proposing the installation of a generation facility contacts PowerStream. PowerStream will provide the Customer with an information package and a Form A - Pre-FIT Consultation Application. The Customer will: |
| 2. | Initial Consultation |
| | |
| | After the Customer has reviewed the information package he develops an installation plan. The Customer will: - Complete and submit the Form A - Pre-FIT Consultation Application to PowerStream
- Contact the Ontario Power Authority (OPA) and complete the OPA FIT application. Once the application is completed the project will be issued a Reference Number.
After PowerStream has reviewed the Form A - Pre-FIT Consultation Application and established the generator classification, the project will be discussed with the Customer in a face to face meeting. The aim of this meeting is discuss issues of mutual interest early in the Customer's review of the feasibility of the project. PowerStream will provide the Customer with a Form B - Connection Impact Assessment Application. |
| | |
| 3. | Connection Impact Assessment |
| | |
| | If the Customer decides to proceed with the project, the Customer submits the completed Form B - Connection Impact Assessment Application and a signed Study Agreement Form with a payment for the Connection Impact Assessment. The cost of the Connection Impact Assessment varies with the size of the generation facility. The amount of the Connection Impact Assessment Fee will be determined at the initial consultation. The Customer is allocated capacity upon completion of the CIA (excludes Micro) by PowerStream's Stations Design department. The capacity allocation for feeder and stations is maintained in accordance with the capacity allocation process shown in Note 1. Renewable generation projects up to and including 250 kW on lines less than 15 kV or up to and including 500 kW on lines greater than or equal to 15 kV, are exempted from the capacity allocation process. |
| | |
| 4. | Connection Cost Estimate |
| | |
| | After the CIA is complete, the scope of work required to connect new generation can be developed and the cost of connection to PowerStream’s distribution system can be estimated. |
| | |
| 5. | Design and Build |
| | |
| | Once agreement of the scope, cost and timing are reached, the Customer is required to sign a Connection Cost Recovery Agreement. After submitting the agreement and payment, detailed design and construction at additions or modification to PowerStream’s distribution system may begin. |
| | |
| 6. | Connect, Operate and Maintain |
| | |
| | Once all of the required work and approvals are completed, a Connection Agreement will be signed by PowerStream and the Customer. The Connection Agreement provides an outline of the connection as well as the roles and responsibility of each party. An Operating Agreement will be developed by PowerStream's Operation's department and signed by both parties. If the generator is one MW or larger, a Transmission Connection Agreement will be developed by PowerStream's Operations department and signed by both parties. |
| | |
microFIT Generators - Connection Process Overview |
| The following is the connection process overview for generators that are less or equal to 10kW and operate at voltages below 50kV: |
| | |
| 1. | Application Process |
| | |
| | The complete microFIT application process is as follows: |
| | |
| | | a) | Customer (Generator) proposing the installation of a generation facility with PowerStream must first contact the Ontario Power Authority (OPA) and complete their microFIT application. | | b) | OPA issues the project a 7-digit FIT reference number when the application is processed. | | c) | Customer submits a Connection Request to PowerStream when the project’s application status is set to “Pending LDC Offer to Connect”. (Connection Request consists of Form C - Micro-Generation Connection Application and Single Line Diagram). | | d) | PowerStream notifies the OPA when the Connection Request Package is received. | | e) | PowerStream provides a Service Design (Offer to Connect) to the customer with the necessary design requirements and construction costs to connect the generator. | | f) | PowerStream informs the OPA when the Connection Request is approved. | | g) | Customer reviews PowerStream requirements and develops an installation plan following receipt of the Application Approval Notice from the OPA. | | h) | Customer pays PowerStream fees as per the Service Design. | | i) | Customer installs the project. | | j) | Customer makes an appointment with New Connections for the Disconnect/Reconnect. | | k) | Generation site approval by ESA. | | l) | PowerStream installs generation meter. | | m) | ustomer completes the Commissioning Verification Form and submits to PowerStream. | | n) | PowerStream issues a Connection Agreement to the customer. | | o) | Customer signs and returns the Connection Agreement to PowerStream. | | p) | PowerStream updates the OPA with the project’s connected status. | | q) | OPA issues a Contract to the customer. | | r) | Customer accepts the OPA Contract. | | s) | OPA informs PowerStream of a new OPA Contract. | | t) | PowerStream starts payments as per PowerStream billing cycle. | |
| 2. | Connection Type |
| | |
| | There are two kinds of microFIT configurations to connect to the electricity system: |
| | |
| | a) Stand-Alone Connection |
| | |
| | The generator is directly connected to the grid and is not connected to the Customer's existing electricity supply. This type of connection requires a separate transformer for the generator. The generator pays all connection costs including the cost of the transformer, as illustrated below.
|
| | |
| | |
| | b) Parallel Connection |
| | |
| | The generator is connected through the Customer's existing electrical system and existing connection to the distribution system. This connection is configured with the generator meter and the load meter electrically in parallel. The electricity produced is sent directly into the distribution system. The customer continues to use electricity from the distribution system for their consumption. Customers connected in parallel will be paid the microFIT contract price for all the electricity produced by the generator and their electricity bill will be calculated in the same manner as prior to the installation of the generator. Payment for the microFIT generation is separate from the bill for electricity consumed.
|
| | 
|
| | |
| 3. | Connect, Operate and Maintain |
| | |
| | Once all of the required work and approvals are completed, a Connection Agreement will be signed by PowerStream and the Customer. The Connection Agreement provides an outline of the connection as well as the roles and responsibilities of each party. |
| | |
| | |
Ý |
|